Without roots in the south of Gran Canaria, they do not even hire cranes in the region, much less clean the dust they raise on the houses and damage to the vehicle fleet. The General Directorate of Energy of the Government of the Canary Islands will continue to fill mills in the south of the island. A company linked to the Portuguese EDP Renováveis promotes the repowering installation of 20 to 20,1 MW of the Llanos de Wind Farm juan big.
The installation requires administrative authorization in accordance with the provisions. What they are going to embed are 2 Enercon model E-70 E4 windmills of 2.300 kW, four 2.800 kVA (0,4/20 kV) transformation units, housed in each wind turbine, dismantling of 19 existing wind turbines and 48 wind turbines being maintained. existing Desa brand. Total installed power 23,6 MW regulated to 20,1 MW.
The connection point: at the REE 66 kV Matorral Substation. 10,5 million euros that will end up in the hands of Las Palmas companies that are suppliers and the German manufacturer of the mills, which is financed by the EU. This is a procedure based on urgent measures to promote the primary, energy, tourism and territorial sectors of the Canary Islands. That is to say: if the neighbors resort, they will lose their money.